LNG
-
Chan May LNG火力発電所を建設へ
トゥアティエン=フエ省フーロク県(Phú Lộc)のチャンマイ・ランコー経済特区(Chân Mây-Lăng Cô)に液化天然ガス(LNG)火力発電所が建設される。投資総額は60億USD(約6200億円)で, ベトナム側40%、米国側60%が株式を保有。フェーズ1(2024-25年)でタービン3基出力2,400MW、2(26-28年)で2基1,600MW。
-
Dung Quat I, III Gas fired power investment decisions
Vietnam Deputy Prime Minister Trinh Dinh Dung has the Dung Quat I & III gas fired power investment Decisions No. 1461 & 1460 / QD-TTg dated 25 October 2019. Two gas power plants in Dung Quat EZ to input gas flow from the Blue Whale field.
Investor: Vietnam Electricity (EVN).
Capacity: 02 x 750 MW (natural gas-fired combined-cycle)
Total investment: 18.663,679 billion VND (Dung Quat gas fired power I). 17.58,76 billion VND (Dung Quat gas fired power III).
Start Construction: Dung Quat I (Jan 2021). Dung Quat III (Jan 2022).
Commercial Operation: Dung Quat I (Dec 2023) Dung Quat III (Dec 2024).
April 29, 2020
Saipem has completed 02 Blue Whale 's FEED packages and handed over to the operator for the next step, prepare and submit for approval of the Field Development Plan (FDP). The scopes of work that ExxonMobil and partners under Production Sharing Contract (PSC) including PVN and PVEP, have been performing for Blue Whale project, as follows:
1/ Geological & geophysical survey, onshore and offshore (done)
2/ Environmental impact assessment (ESHIA & EIA) (done)
3/ Clearance and site preparation for gas treatment plant (GTP), condensate storage (done)
4/ Adjustment progress, implementation plan (to update FDP), and investment milestone (done)
5/ Capital arrangement plan of ExxonMobil, PVN and PVEP in the project chain (being discussed)
6/ Government Guarantee Undertaking Agreement (GGU), and Gas Sale Agreement (GSA) with 3 power plant investors (11st negotiation)
7/ FEED design: Saipem (done)
8/ Article 6.2.9 of the PSC Contract on redetermination of pending period from November 30, 2017 to November 29, 2019 (waiting for approval)
9/ FDP: in 2020 (approval by MOIT)
10 / FID: in 2020 (or early 2021) approval by Viet Nam PM.
The bidding schedule for 2 international packages of EPC (onshore) and EPCIC (offshore) according to FEED design, will likely take place in parallel as tentative plan, as belows:
+ EPC/EPCIC ITB: June 2020
+ EPC/EPCIC Contract Awards: December 2020
+ EPC/EPCIC Performances: 2021 to June 2024
+ Commissioning: July to Oct 2024
+ Handover/commercial operation: November 2024
-
PTSCとサムスンC&T、LNG Thi Vai のEPC契約を獲得
ペトロベトナムガス(PV GAS)、ペトロベトナムテクニカルサービス( PTSC)とサムスンC&Tのジョイントベンチャー(JV)を、LNG Thi Vai の事業の設計、調達、建設工事(EPC)の契約者として選定したと発表した。この契約は、PVGas2019年6月に予定している最終投資決定(FID)を踏まえるという条件付きのものだが。
容量:1,000,000 tons / year.
総投資額が従来計画らみ28500万ドル
EPC契約額:19800万ドル
EPCスケジュール:2019年 - 2022年(36ヶ月)
商業運営:2022年の第3四半期<ティバイLNG受入基地概要>
場 所:ベトナム バ・リア・ブン・タウ省 カイ・メップ工業地域
設備概要:LNGタンク(10万kl×1基)、気化器、LNG船受入バース(桟橋)など
敷地面積:55,000m2Thi Vai 受入基地は Nhon Trach 3 および Nhon Trach 4 発電所(2 x 750MW)向け。
2019年6月24日、サムスンC&Tとペトロベトナムとの間で、「LNG Thi Vaiターミナルロジェクト」の契約調印式がペトロベトナム本社で行われました。
9月28日
PVGas今10月から本格的な工事に着手しますにベトナムのLNG Thi Vai.
10月28日
ペトロベトナム (PVN), PVGas どLNG Thi Vai る の起工式が10月28日。LNG Thi Vai のして2022年秋ごろ竣工する予定です。
-
米ゼネラルエレクトリック、EVN Genco3とLong Son LNG発電所で覚書
ベトナムEVN Genco3の電力大手ゼネラルエレクトリックは22日、部バリア・ブンタウ省のLong Son発電所に液化天然ガス(LNG)を燃料とするガスタービンコンバインドサイクル(CCGT)発電所を建設することで覚書(MOU)を締結した。調印式には米国国家安全保障問題担当補佐官ロバート・オブライエンがベトナムを訪問も立ち会った。このMOUによると、同発電所は総額約10億USD(約1039億円)、出力1500MWの大規模な発電所となる。
このプロジェクトには、Pacific Corporation、ベトナムのPower Engineering Consulting Joint Stock Company 2(PECC2)、およびMitsubishiCorp。のローカルユニットも含まれます。